Twinsburg Division Current Projects

City of Elyria 684020 Lorain County

$17,002,236
State Rt 57 Improvements
125,632 Tons Asphalt
89,000 Sq. Yds. Milling
Completion Date: 10/31/2009


ODOT Project 680119 Portage County

$1,716,175.
SR 14 Improvement, 4.56 miles Planing and Resurfacing
20,683 Tons Asphalt
109,016 Sq. Yds. Milling
Completion Date: 9/30/08


City of Youngstown Project 684045 Mahoning County

$1,543,000
16,787 Tons Asphalt
87,920 Sq. Yds. Milling
Completion Date: 9/2008


ODOT Project 670489 Summit County

$583,483
State Rt. 93/162 City of Akron Improvement
5,120 Tons Asphalt
47,256 Sq. Yds. Milling
Completion Date: 7/30/2008


ODOT Project 680248 Medina/Ashland Counties

$2,729,866
State Rt. 224 Milling, Pavement, Repairs and Resurfacing
165,000 Sq. Yds. Milling
2,000 Cu.Yds. Pavement Repairs
27,000 Tons Asphalt
Completion Date: 8/31/2008


OCOT Project 670415 Stark County

$4,840,694
State Rt. 30 Improvement from the Wayne/Stark County line east 6 miles.
48,598 Tons Asphalt
277,930 Sq. Yds. Milling
Completion Date: 10/15/2008


ODOT Project 060468 Lake County

$25,392,234.
Improvement of SR 2 in the Cities of Wickliffe, Willowick & Eastlake.
Reconsctruction of Roadway & Bridges including 247,000 Sq.Yds. of Milling and 130,000 Tons of Asphalt


ODOT Project 060467 Summit County

$11,025,908.
Reconfigure State Route 8 and Interstate 271 Interchange
The Shelly Company is subcontractor to Beaver Excavating on this $90,000,000. project.
133,000 Sq.Yds. Milling
197,000 Tons Asphalt
Completion Date: 2010